Upcoming Construction
A summary of construction to be expected this upcoming week on 69th Avenue & Anoka Street is as follows (note that dates are subject to changes due to weather, etc.):
Week of June 29:
• Continue Concrete Work
The contractor will continue placing concrete curb and gutter along the south side of 69th Avenue from the Anoka County Park Entrance to County Road H. They will also be placing concrete curb and gutter in the spot repair sections that were removed on the north side of 69th Avenue as well as the sections on Anoka Street.
Upcoming Construction Events
Week of July 6:
• Start final grading for roadway/trail/swale
• Traffic Light Revisions
• Prepare for Paving
Week of July 13:
• Backfill the embankment on northern side of 69th Avenue
Parking
We ask that you do not park cars on 69th Avenue or Anoka Street in construction areas from 7 a.m. to 7 p.m., Monday-Friday to allow for the contractor to have the space needed to complete the project. Street parking causes delays for the contractor and increases the risk of damage to your personal vehicles. Please let us know as soon as possible if you plan on hosting any events (graduation, birthday, holidays, etc.) and we will do our best to work with our contractor to avoid any major inconveniences.
We also ask that you refrain from watering your lawn in areas where if the runoff could go onto the new concrete or gravel road.
Public Works Department – Engineering Division
(763) 572-3554 June 25, 2020
69th Avenue and Anoka Street Rehabilitation Project
Our project engineer, Brandon Brodhag, can be reached at (763) 238-8086 if you have questions.
See the project webpage at fridleymn.gov/projects or contact the City of Fridley Engineering Division at (763) 572-3554
if you need additional information. You may view a project map and sign up for updates to be emailed to you!