The Metropolitan Council Environment Services continue work on the Fridley/Tri City Sewer Improvements covering an approximate 1-mile section of aging and deteriorating sanitary sewer serving Fridley, New Brighton & Mounds View. Upcoming work includes:
Worked planned for March 7 -18:
• Lining a section of sewer near Medtronic's parking lot. Equipment will be set up on the east side of the parking lot and will need to run 24 hrs a day with some noise. Construction in this area is anticipated to be 4 days (March 7-10).
• Pit excavation work continues near 69th Avenue and Shamrock Lane with meter demolition work currently taking place at the excavation in New Brighton near Stinson Blvd and Spring Creek Dr.
• The temporary wastewater conveyance system is operational and is expected to be in use through the first week of April while the pipe rehabilitation work takes place. Pump attendants will be on site monitoring the system 24 hours a day. Noise levels near the pumping locations and along the conveyance pipes will be monitored to ensure compliance with city/regulatory agency requirements.
For questions or concerns about this project, contact info@naiphase5.com or (763) 392-4648.